System contribution surcharge (D3)

The System contribution surcharge is the customer´s share in investments in the transmission grid due to new connections or the reinforcement of the transmission or distribution system.

On July 1st 2018 a new grid code regarding the system contribution surcharge for producers and power intensive users connected to the grid was released. The ESA requires the publication of the methodology and calculations on the system contribution surcharge to ensure transparency and equality. The grid code formalizes the methodology that has been used to determine the surcharge.

The grid code was published on July 1st 2018 following confirmation from the Ministry.

If you have any question please do not hesitate to contact us at vidskipti@landsnet.is

Time Schedule

Writing and consultation [2016]

Customer review process finished December 13th 2016

Review of comments, update of the grid code and reaction to comments from customers finished in 2017

The grid code was sent for an approval to the ministery in the beginning of February 2018

Publication was on July 1st 2018

 